Denis Yu. Samoilov
|
ASOI, ”Global Business Technology” LLC |
Almetyevsk, Russian Federation samoilovdy@tatintec.ru |
Vladimir V. Samoilov
|
”Global Business Technology” LLC |
Almetyevsk, Russian Federation samoilov@tatintec.ru |
Vasiliy S. Voronkov
|
Field office “Leninogorskneft”, “Tatneft” |
Leninogorsk, Russian Federation irntodn@tatneft.ru |
Farit A. Galiev
|
Field office “Leninogorskneft”, “Tatneft” |
Leninogorsk, Russian Federation intodn@mail.ru |
The article describes the application of the reservoir pressure waves (RPW) method to increase oil recovery of fields with high water cut. Developed automated control system allowed realizing a RPW method for oil production well. Obtained the effect to reduce the water cut of production wells.
Materials and methods
Analysis of the results of field research.
Results
The resulting effect of reducing the water cut in production wells by means of the RPW method and designed control system.
Сonclusions
1. Developed control system allows implementing a RPW method and increase oil recovery for reservoir with high water cut.
2. To assess the effectiveness of the RPW method required the using of wellhead water cut measuring device.
3. Most modern control systems of well operation allow increasing the production rate by reducing downtime of wells and partly by filling of the pump. However, these systems do not provide reduction of water cut.
control system of well operation
reservoir pressure wave
increase oil recovery
non-stationary well operation